Spring/Dove Creek - Twin Buttes
Objective:
2007 EQIP funds will be used to support brush control efforts in selected
watersheds. Initial efforts will focus on cost share for initial and follow-up
brush control. EQIP funds will be utilized to increase available water through
brush control and grazing management.
Eligibility-
Approved Project Watersheds
Twin Buttes
Spring and Dove Creek
Resource Concern:
Water Quantity (Ground and Surface Water)Primary Area of Concern:
Initial Brush Management – all approved methods on juniper, mesquite and
prickly pear - High Priority
Follow-up Brush Management - Medium Priority
Facilitating practices [range planting, water development, fence, grazing land mechanical treatment (ripping), prescribed burning]
-
Low Priority
Eligible Practices:
Brush Management (314)
Range Planting (550)
Fence (386)
Watering Facility (614)
Water Well (642)
Grazing Land Mechanical Treatment (548)
Prescribed Burning (338)
Pipeline (516)
Prescribed Grazing (528A)
Cost Share Rates:
Limited Resource Farmer/ Producer - 90 percent
Beginning Farmer/ Rancher - 50 percent
All other categories - 50 percent
Practices will be cost shared based on the established county average cost of
the practice.
Ranking Criteria:
| Criteria |
Points |
| Brush Management: |
|
| Initial Brush Management on juniper and
mesquite |
150 points |
| Prickly pear control |
125 points |
| Follow-up Brush Management - 50 plants per acre or greater than 11
percent density |
70 points |
| Facilitating Practices: |
|
| Range planting |
15 points |
| Fencing |
15 points |
| Water Development |
15 points |
| Grazing land mechanical treatment |
15 points |
| Prescribed burning |
15 points |
| Incentive Practice: |
|
Prescribed Grazing $5 per acre -
See Job Sheet |
50 points |
| Score: |
________ |
Ranking Worksheet
Only highest point item counts toward score
Can have multiple item contracts
60 percent of total contract dollars must address the high priority concern
Mark all practices that producer wants to cost share
Prescribe Grazing
points are in addition to highest point item
*Follow-up Brush Management - 50 plants per acre or greater than 11
percent
density
| |
|